          Manajemen Risiko
          Risk Management


         Jenis Risiko yang Dihadapi Perusahaan dan Mitigasinya
         Types of Risks Exposed to the Company and Their Mitigation

         Dari hasil identifikasi risiko, diperoleh 13 risiko utama Perusahaan   Based on these results, the Company identified a total 13 key risks.
         yang terbagi dalam kelompok sangat tinggi sebanyak 5 (lima)   They were divided into two groups; 5 (five) “Very High” risks and
         risiko dan kelompok tinggi sebanyak 8 (delapan) risiko. Perusahaan   8 (eight) “High” risks. The Company has managed those risks,
         telah melaksanakan pengelolaan risiko-risiko tersebut, termasuk   including implementing the mitigations, as follows:
         melakukan mitigasi risiko, sebagai berikut:

            ID Risk     Deskripsi Risiko                                Mitigasi
            Risk ID     Risk Description                               Mitigation
          O.5      Terjadi Force Outages   Program Revitalisasi, Retrofit, Rehabilitasi dan modifikasi peralatan pembangkit
                   atau Derating Akibat   Revitalizing, Retrofit, Rehabilitation, and Modification of Power Plant Equipment Programs
                   Ketidaksiapan dan     Program Upgrading & Penggantian Part kritikal pada Peralatan Utama
                   Gangguan Peralatan    Main Equipment’s Critical Parts Replacement & Upgrade Programs
                   Pembangkit menjadikan
                   target operasional    Assesment pada peralatan utama pembangkit.
                   pembangkit tidak tercapai  Assessment of Power Plant Main Equipment
                   Power Outages or Derating  Kapitalisir Overhaul Unit Pembangkit.
                   Due to Unpreparedness   Capitalizing of Power Plant Unit Overhaul
                   and Disturbances of   Retubing Boiler PLTU.  SPP Boiler Retubing
                   Power Plant Equipment
                   resulted in the failure to   Pengadaan Strategic Parts peralatan - peralatan kritikal.
                   achieve power generator   Critical Equipment Strategic Parts Procurement
                   operational target.
                                         Pengadaan Material, Tools dan Jasa Overhaul Tahun 2022
                                         Procurement of Material, Tools, and Overhaul Services in 2022
                                         Pelaksanaan Over Haul sesuai prinsip 5ON.
                                         Implementing Overhaul in accordance with the principles of 5ON
                                         Penggantian Peralatan Utama yang telah Obsolence.
                                         Replacement of Obsolete Main Equipment
          O.5.7.1  Penurunan Efisiensi   Pengadaan Material dan Jasa perbaikan Peralatan Boiler dan Furnace
                   Pembangkit yang       Procurement of Material and Equipment Repair Services for Boiler and Furnace
                   berdampak pada        Pengadaan Strategic Part Sootblower.  Sootblower Strategic Parts Procurement
                   peningkatan BPP
                   Perusahaan            Pengadaan Intermediate element air preheater
                   Declining Efficiency of   Procurement of Intermediate element air pre-heater
                   Power Plants resulted   Replacement PCV Reheat Spray Unit 4 PLTU Suralaya
                   in the increased power   Replacement of PCV Reheat Spray Unit 4 of SPP Suralaya
                   generation supply cost of   Penggantian Valve dan Pipa drain area Boiler dan Turbin PLTU
                   the Company.          Replacement of Valves and Drain pipes in Boiler area and Turbine of SPP
                                         Pengadaan Oxygen Analyzer. Procurement of Oxygen Analyzer
                                         Optimasi pemakaian sendiri. Self-consumption optimization
          S.3.6    Terancamnya           Marketing produk beyond kWh berupa Jasa O&M, MRO, dan ODP ke Pasar Potensial (IPP,
                   keberlangsungan       Pembangkit Captive, dll)
                   usaha perusahaan      Marketing the products of beyond kWh, including O&M Service, MRO, and ODP to Potential
                   yang berdampak pada   Markets (IPP, Captive Power, etc.)
                   menurunnya market     Pengembangan Bisnis beyond kWh di dalam dan di Luar Negeri
                   share dan pendapatan   Beyond kWh Business Development across the country and overseas
                   perusahaan
                   The impending danger   Pengembangan Bisnis Solar PV Manufacturing
                   to the sustainability of   Solar PV Manufacturing Business Development
                   corporate business led to   Pengembangan Pembangkit MPP & BMPP.
                   the declining market share   Mobile Power Plant (MPP) and Barge Mounted Power Plant (BMPP) Development
                   and corporate earnings.  Relokasi Pembangkit Grati ke Bali. Relocation of Grati Power Plant to Bali