          Tinjauan Kinerja Operasi Per Segmen
          Operational Performance Overview by Segment


          Equivalent Availability Factor (EAF)               Equivalent Availability Factor (EAF)
          Pembangkit Jasa O&M Jawa                           of O&M Service Power Plants in Java

          Semakin tinggi nilai EAF menunjukkan tingkat kesiapan   Higher EAF score indicates better readiness of the power plant.
          pembangkit lebih baik.

          Equivalent Availability Factor (EAF) pembangkit jasa O&M Jawa   The Equivalent Availability Factor (EAF) of O&M Service power
          tahun 2022 sebesar 91,05% yaitu meningkat 1,35% dibandingkan   plants in Java in 2022 was 91.05%, which was higher by 1.35%
          tahun 2021. Peningkatan tersebut terutama disebabkan karena   than in 2021. This was due to the absence of overhaul works in SPP
          tidak adanya pekerjaan overhaul di Banten 1 Suralaya PGU selama   Banten 1 Suralaya PGU throughout 2022.
          tahun 2022.

         Tabel EAF Unit Pembangkit Jasa O&M Jawa Tahun 2019 - 2022 (%)
         Table of Java O&M Service Generation Unit EAF in 2019-2022 (%)

                        Unit Pembangkit              2019       2020        2021       2022      Pertumbuhan
                        Generation Unit                                                            Growth
          Banten 1 Suralaya PGU                         55,79      71,40      59,22       69,42    17,22%
          Banten 2 Labuan PGU                           79,85      90,02      84,39       88,93    5,38%
          Banten 3 Lontar POMU                         92,94       83,28      94,70       90,00    (4,96)%
          Jawa Barat 2 Pelabuhan Ratu PGU              83,38       90,97      91,23       91,34    0,12%
          West Java 2 Pelabuhan Ratu PGU
          Jawa Tengah 2 Adipala PGU                    93,83       85,17      86,20       88,81    3,03%
          Central Java 2 Adipala PGU
          Priok Blok 3 PGU Priok Block 3 PGU            84,44      93,74       92,04      97,40    5,82%
          Priok Blok 4 PGU Priok Block 4 PGU           86,95        97,41      96,12      95,18    (0,98)%
          Cilegon PGU                                   91,84      95,82       98,69      95,43    (3,30)%
          Grati Blok 3 PGU Grati Block 3 PGU           89,83       99,26       99,95     100,00    0,05%
          Jumlah EAF Pembangkit Jasa O&M Jawa          84,72      89,80       89,84      91,05     1,35%
          Total EAF of O&M Service Power Plants in Java

          Scheduled Outage Factor (SOF)                      Scheduled Outage Factor (SOF)
          Pembangkit Jasa O&M Jawa                           of O&M Service Power Plants in Java

          Semakin rendah nilai SOF menunjukkan unit pembangkit dapat   Lower SOF indicates better generation unit’s performance in
          melakukan optimasi dalam pemeliharaan yang direncanakan.   optimizing the planned maintenance.

          Scheduled Outage Factor (SOF) pembangkit jasa O&M Jawa tahun   The Scheduled Outage Factor (SOF) of O&M Service power plants
          2022 sebesar 6,15% yaitu lebih rendah 20,75% dibandingkan   in Java in 2022 was 6.15%, which was lower by 20.75% than in 2021.
          tahun 2021. Hal tersebut terutama disebabkan karena tidak adanya   This was due to the absence of overhaul works in Banten 1 Suralaya
          pekerjaan overhaul di Banten 1 Suralaya PGU selama tahun 2022.  PGU throughout 2022.


          Tabel SOF Unit Pembangkit Jasa O&M Jawa Tahun 2019 - 2022 (%)
          Table of Java O&M Service Generation Unit SOF in 2019-2022 (%)

                        Unit Pembangkit              2019       2020        2021       2022      Pertumbuhan
                        Generation Unit                                                            Growth

          Banten 1 Suralaya PGU                         17,77       6,91      29,93       10,91   (63,55)%
          Banten 2 Labuan PGU                           6,83        2,81       13,75      10,89   (20,80)%
          Banten 3 Lontar POMU                           2,31      12,64        3,00       9,22   207,33%