Page 206 - Sustainability Report 2021 - Indonesia Power
P. 206
Menghadirkan Keberlanjutan
Lingkungan Menuju Karbon Netral
PENGELOLAAN PENGGUNAAN DAN EFISIENSI ENERGI
ENERGY CONSUMPTION AND EFFICIENCY MANAGEMENT
Nilai Efisiensi Energi Tahunan (Gigajoule)
Unit Kerja Jenis Energi Program PPME Annual Energy Efficiency (Gigajoules)
No
Work Unit Energy Type PPME Program
2018 2019 2020 2021
12 PLTU Pelabuhan Ratu Batubara - Penggantian Long Sootblower Unit 28.858.964,67 25.037.324,39 60.288.220,24 44.250.731,17
OMU Coal 3 - R7
- Inspeksi Total Burner Tiliting -
Corner 1
- Program inovasi lainnya
- Replacement of Long Sootblower
Unit 3 - R7
- Inspection of Total Burner Tiliting -
Corner 1
- Other innovation programs
13 PLTU Adipala OMU Batubara - Penggantian safety valve HPH 8 - 1.306.889,09 262.930,08 400.303,62
Coal - Simple inspeksi (SI) air preheater A
- Program inovasi lainnya
- Replacement of HPH 8 safety valve
- Simple inspection (SI) of air
preheater A
- Other innovation programs
14 PLTGU Cilegon OMU Gas - Modifikasi Tripod Inlet Air Filter GT 2.805.713,65 4.319.574,27 1.587.877,19 101.844,30
Gas 1.2
- Penggantian Motor Actuator HRSG
1.2 IP continous blow down
- Program inovasi lainnya
- Modification of Tripod Inlet Air Filter
GT 1.2
- HRSG 1.2 IP continuous blow down
Actuator Motor Replacement
- Other innovation programs
15 PLTU Pangkalan Susu Batubara - Penggantian cold element APH 2A - 1.119.736,17 270.195,33 310.933,78
OMU Coal Unit 2
- Rehabilitasi orifice coal pipe all mill
Unit 2
- Program inovasi lainnya
- Replacement of cold element of APH
2A Unit 2
- Rehabilitation of orifice coal pipe all
mill Unit 2
- Other innovation programs
16 PLTU Barru OMU Batubara - Revitalisasi Chlorine Plant - - 313.224,05 67.475,38
Coal - Cleaning kondensor unit 2
- Program inovasi lainnya
- Revitalizing Chlorine Plant
- Cleaning condenser unit 2
- Other innovation programs
17 PLTU Sanggau OMU Batubara - Inspection dan perbaikan MOV - - 55.886,79 3.891,17
Coal Extraction Steam HP Heater
- Inspection vacuum ejector
- Program inovasi lainnya
- Inspection and repair of MOV
Extraction Steam HP Heater
- Inspection vacuum ejector
- Other innovation programs
18 PLTU Jeranjang OMU Batubara - Rencana pengecekan di safety valve - - 794.635,35 12.722,82
Coal boiler
- Improvement condensor vacuum
Unit 1
- Program inovasi lainnya
- Check up plan in safety valve boiler
- Improvement condenser vacuum
Unit 1
- Other innovation programs
206 Lapooran Keberlanjutan 2021 PT INDONESIA POWER