          Perkara Hukum dan Sanksi Administratif yang Dihadapi
          Legal Disputes and Administrative Sanctions Faced by the Company



                                                                                                Risiko yang dihadapi
                                 Jenis Perkara
                 Pihak yang Berperkara         Pokok Permasalahan     Status Penyelesaian  Sanksi  Perusahaan
           No.                     Type of
                  Disputing Parties                 Issue             Settlement Status  Sanction  Risk Exposed to the
                                   Dispute
                                                                                                   Company
           5.  PT Poros Maritim Logistik   Perdata (BANI)   Permohonan Arbitrase (Perbuatan   Bahwa para pihak membuat perjanjian   Tidak Ada  Pelaksanaan Putusan
               – PT Bumi Sentosa Dwi   Perbuatan   Melawan Hukum) PT Poros Maritim   perdamaian berupa Akta Kesepakatan   BANI
               Agung (Joint Operation)   Melawan   Logistik – PT Bumi Sentosa Dwi   Bersama tertanggal 17 Oktober 2022   None
               sebagai Pemohon melawan   Hukum   Agung (Joint Operation) sebagai   dalam perkara Arbitrase (Perbuatan   Implementation of
               PT Dahana (Persero) sebagai   Pemohon melawan PT Dahana   Melawan Hukum) PT Poros Maritim   BANI’s Award
               Termohon I dan PT Indonesia   Civil Case   (Persero) sebagai Termohon I dan  Logistik – PT Bumi Sentosa Dwi Agung
               Power (Persero) sebagai   (BANI) against   PT Indonesia Power (Persero)   (Joint Operation) sebagai Pemohon
               Termohon II       Unlawful Act  sebagai Termohon II yang diajukan   melawan PT Dahana (Persero) sebagai
                                           melalui BANI pada tanggal   Termohon I dan PT Indonesia Power
               Register Perkara Nomor:     08 Juni 2022 dengan register   (Persero) sebagai Termohon I yang
               45047/VI/ARB-BANI/2022      perkara Nomor: 45047/VI/ARB-  telah disepakati dan ditandatangani
                                           BANI/2022 yang mana Pemohon   oleh Pemohon, TermohonI dan
               PT Poros Maritim Logistik –   selaku Subkon dari pekerjaan Cut   Termohon II yang dituangkan dalam
               PT Bumi Sentosa Dwi Agung   & Fill (Pemotongan dan Perataan   Putusan Badan Arbitrase Nasional
               (Joint Operation) as the    Lahan) Suralaya 2 x 1000 MW   Indonesia (BANI) Nomor: 45047/VI/
               Claimant against PT Dahana   meminta perubahan pembayaran   ARB-BANI/2022 yang diputuskan dan
               (Persero) as the Respondent I   atas Pekerjaan Perlindungan   diucapkan pada hari Senin tanggal 24
               and PT PLN Indonesia Power   dan Pengamanan Lereng yaitu   Oktober 2022.
               (Persero) as the Respondent   shotcrete seluas 25.279,3 m .
                                                           2
               II                                                That the parties agreed on an
                                           Kemudian dimintakan dibayar   amicable agreement set down in the
               Case Register No. 45047/VI/  kepada Termohon I agar   Agreement Deed dated October 17,
               ARB-BANI/2022               selanjutnya dibayarkan kepada   2022 in the Arbitration case (against
                                           Pemohon, mengingat ada luasan   Unlawful Act) of PT Poros Maritim
                                           shotcrete yang tidak sesuai   Logistik – PT Bumi Sentosa Dwi Agung
                                           spesifikasi teknis maka Termohon   (Joint Operation), as the Claimant
                                           II tidak membayarkan kepada   against PT Dahana (Persero) as the
                                           Termohon I, namun dari Pemohon   Respondent I and PT PLN Indonesia
                                           telah ada prestasi dan Termohon   Power (Persero) as the Respondent
                                           II mendapatkan manfaat atas   II. The Agreement Deed was agreed
                                           Pekerjaan Perlindungan dan   on and signed by the Claimant,
                                           Pengamanan Lereng meskipun   Respondent I, and Respondent II,
                                           tidak sesuai spesifikasi pada   as stipulated in the Award of the
                                           perjanjian.           Indonesian Arbitration Center (BANI)
                                           The Request for Arbitration   No.: 45047/VI/ARB-BANI/2022 made
                                           (against Unlawful Act) of PT Poros   and announced on Monday, dated
                                           Maritim Logistik – PT Bumi Sentosa   October 24, 2022.
                                           Dwi Agung (Joint Operation) as
                                           the Claimant against PT Dahana
                                           (Persero) as the Respondent I and
                                           PT PLN Indonesia Power (Persero)
                                           as the Respondent II was filed
                                           through BANI dated June 08, 2022
                                           on the Case Register No. 45047/
                                           VI/ARB-BANI/2022. The Claimant,
                                           as the Subcontractor for the work
                                           of Cut & Fill (Land) in Suralaya 2 x
                                           1000 MW, requested for a change
                                           of payment for the work of Slopes
                                           Protection and Safeguarding, i.e.,
                                           shotcrete of 25,279.3 m .
                                                         2
                                           The request was that payment
                                           is made to the Claimant by the
                                           Respondent I, considering that
                                           some parts of the shotcrete were
                                           not in line with the technical
                                           specifications, leading to the
                                           unpaid work by Respondent II
                                           to the Respondent I. However,
                                           the Claimant had performed the
                                           work, and the Respondent II had
                                           received the benefit of the work of
                                           Slopes Protection and Safeguarding
                                           even though it did not meet the
                                           specifications on the agreement.





       492      Laporan Tahunan 2022                                                          www.plnindonesiapower.co.id
                PT PLN Indonesia Power
   487   488   489   490   491   492   493   494   495   496   497