Page 263 - Annual Report 2022 - PLN Indonesia Power
P. 263
Analisis dan Pembahasan Manajemen
Management Discussion and Analysis
Tinjauan Kinerja Operasi Per Segmen
Operational Performance Overview by Segment
Tabel SdOF Unit Pembangkit Jasa O&M Luar Jawa Tahun 2019 - 2022 (kali)
Table of Outside Java O&M Service Generation Unit SdOF in 2019-2022 (frequency)
Unit Pembangkit 2019 2020 2021 2022 Pertumbuhan
Generation Unit Growth
Pangkalan Susu 1-2 PGU 8,00 4,50 2,25 8,00 255,56%
Pangkalan Susu 3-4 PGU - - - 5,00 -
Barru POMU 3,50 0,50 1,00 1,00 -
Jeranjang OMU 6,00 7,00 3,67 4,00 8,99%
Sanggau PGU 2,50 2,50 4,00 3,00 (25,00)%
Sintang PGU 1,67 2,33 2,00 1,33 (33,50)%
Holtekamp OMU 3,00 4,00 4,00 4,00 -
Berau PGU - - 8,00 9,00 12,50%
Ulumbu Sub-Unit Kamojang POMU 10,50 9,00 4,50 4,50 -
Jumlah SdOF Pembangkit Jasa O&M Luar Jawa 5,56 4,26 4,11 4,55 10,71
Total SdOF of O&M Service Power Plants outside Java
Tara Kalor Neto Pembangkit Jasa O&M Luar Jawa Net Heat Rate of O&M Service Power Plants outside Java
Semakin rendah nilai Tara Kalor Netto menunjukkan bahwa The lower the net heat rate, the more efficient the power plant.
pembangkit tersebut semakin efisien.
Tara Kalor pembangkit jasa O&M Luar Jawa tahun 2022 sebanyak The Net Heat Rate of O&M Service power plants outside Java
3.890,70 kCal/kWh yaitu lebih rendah 1,54% dibandingkan tahun in 2022 was 3,890.70 kCal/kWh, which was 1.54% lower than
2021. Hal tersebut terutama disebabkan oleh adanya kenaikan in 2021. This was due to increased production and implemented
produksi dan pelaksanaan program efisiensi. efficiency program.
Tabel Tara Kalor Unit Pembangkit Jasa O&M Luar Jawa Tahun 2019 - 2022 (kCal/kWh)
Table of Outside Java O&M Service Generation Unit Net Heat Rate in 2019-2022 (kCal/kWh)
Unit Pembangkit 2019 2020 2021 2022 Pertumbuhan
Generation Unit Growth
Pangkalan Susu 1-2 PGU 3.615,25 3.628,10 3.557,92 3.391,29 (4,68)%
Pangkalan Susu 3-4 PGU - - - 3.299,78 -
Barru POMU 4.311,91 4.387,65 4.537,73 4.200,32 (7,44)%
Jeranjang OMU 3.923,02 3.966,57 4.081,47 4.415,82 8,19%
Sanggau PGU 7.134,89 6.607,20 5.538,40 5.842,02 5,48%
Sintang PGU 5.695,49 5.932,12 5.559,96 6.027,25 8,40%
Berau PGU - - 5.797,49 6.325,85 9,11%
Jumlah Tara Kalor Pembangkit Jasa O&M Luar Jawa 4.936,11 4.904,33 3.951,63 3.890,70 (1,54)%
Total Net Heat Rate of O&M Service Power Plants
outside Java
2022 Annual Report
www.plnindonesiapower.co.id 263
PT PLN Indonesia Power