Page 37 - Annual Report 2022 - PLN Indonesia Power
P. 37
Powering Sustainable Pendahuluan
P
endahuluan
and Prosperous Future Intr oduction
Introduction
PLN Indonesia Power mendapatkan amanah pemegang saham untuk PLN Indonesia Power has received a mandate from the Shareholders
mendukung suksesnya Konferensi Tingkat Tinggi (KTT) G20 pada to help preparing a successful G20 Summit in October 2022,
Oktober 2022, yaitu dengan melakukan relokasi Pembangkit Listrik through the relocation of 2x100 MW Gas Turbine Power Plant
Tenaga Gas (PLTG) dari Grati ke Pesanggaran dengan kapasitas 2x100 (GTPP) from Grati to Pesanggaran, the construction of Hybrid Solar
MW dan membangun Pembangkit Listrik Tenaga Surya (PLTS) hybrid Power Plants (SoPP) of 3.5 MWac for SoPP and 3 MW for BESS
dengan kapasitas PLTS 3,5 MWac dan BESS (Battery Energy Storage (Battery Energy Storage System), and the establishment of Floating
System) 3 MW serta PLTS Terapung Muara Tukad Nusa Dua (100 SoPP Muara Tukad Nusa Dua (100 kWp). These power plants
kWp). Pembangkit tersebut meningkatkan keandalan pasokan listrik di improve the reliability of Bali electricity supply for the G20 Summit
Bali demi suksesnya perhelatan acara KTT G20 yang diselenggarakan on November 15-16, 2022. The SoPPs were also showcased to the
pada 15-16 November 2022. Selain itu, PLTS juga menjadi salah international participants as evidence that the Company is prepared
satu showcase yang diperlihatkan kepada dunia untuk menunjukkan to assist Indonesia’s energy transition toward a new and renewable
Perusahaan siap mengawal transisi energi Indonesia menuju era energi energy (NRE) era.
baru dan terbarukan (EBT).
PLTS Terapung Muara Tukad, Nusa Dua dibangun dengan kapasitas The Floating SoPP of Muara Tukad, Nusa Dua was constructed at
100 kWp di atas bibir pantai Kuta seluas 350 meter persegi. PLTS the capacity of 100 kWp on the shoreline of Kuta Beach, occupying
yang terdiri dari 228 panel solarcell merupakan salah satu program 350 meter square of land. The SoPP which consists of 288 solar cell
dari transformasi PLN yang menggunakan teknologi sistem digital panels is a part of PLN’s transformation program which leverages
untuk memonitor dan mengelola pasokan energi listrik sesuai dengan digital system technology to monitor and manage electricity supply
kebutuhan beban. Proyek PLTS ini juga wujud komitmen PLN Indonesia according to load demands. The SoPP project is also an embodiment
Power terhadap prinsip Environmental, Social and Governance (ESG) of PLN Indonesia Power’s commitment to maintaining the
dalam menciptakan pembangunan ekonomi yang berkelanjutan. Environmental, Social, and Governance (ESG) principles in creating
a sustainable economic development.
PLTS Hybrid Nusa Penida berkapasitas 3,5 MWac dibangun di atas Hybrid SoPP Nusa Penida of 3.5 MWac capacity has been
lahan seluas 4,5 hektare (ha) milik PLN Indonesia Power di Desa constructed on 4.5 hectare of land owned by PLN Indonesia Power
Suana, Kecamatan Nusa Penida, Kabupaten Klungkung, Provinsi in Suana Village, Nusa Penida Subdistrict, Klungkung District, Bali.
Bali. Hadirnya PLTS Hybrid ini akan turut menurunkan emisi karbon The hybrid SoPP is expected to reduce 3,200 ton CO2 of carbon
sebesar 3.200 ton CO per tahun. Proyek ini beroperasi komersial pada emissions annually. The project is commercially operate in October
2
Oktober 2022, sedangkan relokasi PLTG Grati Blok 1 dengan kapasitas 2022, while the relocation of GPP Grati Block 1 of 2x100 MW
2 X 100 MW ke Pesanggaran untuk unit pertama selesai pada Oktober capacity to Pesanggaran is completed in October 2022 for the first
2022, dan unit kedua pada 2023. Proyek ini dibangun di atas lahan Unit, and 2023 for the second Unit. The project will be constructed
seluas 1,9 ha milik Pemda Bali dan milik PLN Indonesia Power. on 1.9 hectare of land owned by Bali Regional Government and PLN
Indonesia Power.
2022 Annual Report
www.plnindonesiapower.co.id 37
PT PLN Indonesia Power